Independent customer review. Not affiliated with, sponsored by or endorsed by L&G Building & Concrete. How this site is sourced

LG Building & Concrete Review

How to read a metal building quote, line by line

My order form has thirty lines, a discount bigger than a car, and a $0 line that cost me $2,000 and a dispute. Here is how to read one.

Where this comes from

My project record

Metal building quotes are built from a configurator: pick a size, add options, apply a discount. The result looks precise. The precision is in the options list; the risk is in what the list leaves out.

Start at the bottom

My line items total $92,182.50. A single line, “Manufacturer Discount,” removes $41,631.50. The building total is $50,551. The discount is a pricing convention, not a bargain; compare bottom lines between sellers for the same size, height, gauge, roof style and certification, and ignore the size of anyone’s discount.

Find the structure lines

Base building ($36,300 at list for my 50×80, 14 gauge, vertical roof, 3/12 pitch). Height ($8,400 for 16-foot legs). Closed ends and sides ($9,420 and $8,060). Lean-tos with their own height, gables and side walls (about $18,350 for my two). These are the lines that decide what you are getting; everything else is detail.

Openings are not doors

My order has ten garage-door frame-outs, priced $400 to $600 each, and two walk-in doors. A frame-out is the framed hole. The roll-up door that goes in it is not on my order at all. Ask what every “frame-out” line will cost to fill.

Read every $0 line as a cost

“7k Telehandler Lift (customer Provided), $0.” “Other Certification, $0.” “Soffit, wainscot, J-trim, ladder-leg baserail, FREE.” The lift was $2,000 of rental and the center of my dispute. Zero on a quote means the seller is not charging for it, not that it is free.

Look for the sales tax line

Mine says none charged. The packet includes a North Carolina capital-improvement affidavit, which is the tax paperwork for treating the job as a real property contract. Understand what you are signing there; it describes the work as performed by a real property contractor.

Five things a quote should have and mine did not

  • A license number.
  • A delivery date for engineered plans and a start window for construction.
  • Who supplies the lift and for how long, priced.
  • The concrete specification on the same page as the building, with the foundation sheet referenced.
  • A completion date and what happens if it is missed.

Why a customer wrote this

In February 2026 I signed a $98,750 contract with L&G Building & Concrete of Asheboro, North Carolina. By September I had a cracked slab, damaged plumbing and half a steel frame. This site documents it, with the contract, photos, texts and public records. The resources exist so the next buyer does not need to learn the same things the same way.

General information from one customer’s experience and research. Not legal, engineering or financial advice.